Kern Valley State Prison Solar Project
3 Documents in Project
Summary
SCH Number
2018081046
Lead Agency
Department of General Services
(DGS)
Document Title
Kern Valley State Prison Solar Project
Document Type
NOD - Notice of Determination
Received
Posted
10/2/2018
Document Description
The proposed project is a solar PV power generation system to be located on approx 26 acres of land at the address of 3000 W Cecil Ave, Delano, CA 93215 which is part of the large state-owned Kern Valley State Prison facility. The ground-mounted solar array would convert sunlight to direct current electrical power which would then be converted to alternating current by string inverters before being delivered to the PG&E distribution system. The total system size is expected to be approx 2.95 mw (AC), subject to final design and site optimization.
The solar system would be configured into six generally contiguous arrays. The solar system will utilize either fixed-tilt or single-axis tracking mounting technology to optimize efficiency and performance. The ground-mounted arrays would be supported on drive pipe piles, drive H-piles, or reinforced-concrete cast-in-drilled-hole piers, with the foundation design to be finalized following completion of on-site geotechnical surveys.
Contact Information
Name
Terry Ash
Agency Name
Department of General Services
Contact Types
Lead/Public Agency
Phone
Location
Cities
Delano
Counties
Kern
Cross Streets
W. Cecil Ave
Zip
93216
Total Acres
9.5
Parcel #
520-120-07-01-6
Notice of Determination
Approving Agency
DGS
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.