Upper San Leandro (USL) Seismic Control Valve Project
Summary
                SCH Number
            
            
                2020060218
            
        
                    Public Agency
            
            
                East Bay Municipal Utility District
                (EBMUD)
            
        
                Document Title
            
            Upper San Leandro (USL) Seismic Control Valve Project
        
                Document Type
            
            
                NOE - Notice of Exemption
            
        
                Received
            
            
                    Posted
                
                
                    6/11/2020
                
            
                Document Description
            
            The Project will install a seismic accelerometer, 25 kilowatt emergency generator, 100 gallon propane fuel tank, and associated paving and fencing. The purpose of the Project is to automatically close the existing motor operated valves at the USL Reservoir outlet tower and prevent the release of water from USL Reservoir in the event of an earthquake induced pipeline failure. See Attachment A for additional information.
        Contact Information
                        Name
                    
                    
                        Shelly Dean
                    
                
                        Agency Name
                    
                    
                        East Bay Municipal Utility District
                    
                
                        Contact Types
                    
                    
                        Lead/Public Agency
                    
                
                            Phone
                        
                        
                    
                            Email
                        
                        
                    
                        Name
                    
                    
                        Agency Name
                    
                    
                        East Bay Municipal Utility District
                    
                
                        Contact Types
                    
                    
                        Project Applicant
                    
                Location
                    Counties
                
                Alameda
            
                    Regions
                
                Northern California
            
                    Other Location Info
                
                
                    Shore of USL Reservoir on EBMUD-owned watershed land, Alameda County, see attached Figure 1.
                
            
                    Other Information
                
                
                    The Project site is located off Redwood Road through an EBMUD access road which leads to the shore of USL Reservoir near the USL Reservoir outlet tower (see Figure 1). The access road will be used for worker and equipment access for the Project.
USL Reservoir Water Supply: USL Reservoir is one of the critical storage elements of EBMUD's water supply system and has a capacity of approximately 38,905 acre feet. The flow of water from USL Reservoir to the USL Water Treatment Plant (WTP) is regulated by the USL Reservoir outlet tower, which is a 94-foot-high concrete tower equipped with a series of valves and connected at its base to an outlet tunnel. From the USL Reservoir outlet tower, untreated water flows through a 54-inch diameter tunnel for approximately 1.3 miles before reaching the "West Portal" in Oakland, where the tunnel transitions to a pipeline for approximately 1 mile before reaching the USL WTP in Oakland.
                
            Notice of Exemption
                            Exempt Status
                        
                        
                            Categorical Exemption
                        
                    
                            Type, Section or Code
                        
                        
                            15301 and 15303
                        
                    
                            Reasons for Exemption
                        
                        
                            Reasons why project is exempt: The Project is exempt under 15301 because it involves no expansion of the USL Reservoir's capacity and entails the repair and minor alteration of an existing public facility. The project is also exempt under 15303, since it involves the construction and location of limited numbers of new small facilities or structures. The Project will have no significant environmental effects relative to location, cumulative impact, or significant effects due to unusual circumstances, hazardous waste, or historical resources, pursuant to Section
15300.2 of the CEQA Guidelines.
                        
                    